KASKA is a professional service provider in engineering, constructing and operating rooftop, industrial and free field Solar PV systems. Working professionally around EU. KASKA has references over 490 MWp. Soil testing, pile driving, construction and modules installations, DC and AC electric installations. Own machinery, experienced crew, great history and experiences. Always in time.

Lelystad (NL)

  • 28 MWp east/west system
  • June 2018 - September 2019 – mechanic installation, DC cabling

Pafos (Cyprus)

  • carport 0,1 MWp
  • June 2019 – mechanic installation

Lelystad (NL)

  • 30 MWp
  • September 2018 - March 2019 – complete mechanic installation

Limelette (BE)

  • 0,5 MWp
  • December 2018 - January 2019 – complete mechanic installation and DC

Trogen (DE)

  • 10 MWp
  • November - December 2018 – complete mechanic installation

Estonia (EST) - several projects

  • 2,1 MWp
  • November - December 2018 – complete mechanic installation

Ooltgensplaat (NL)

  • 37,6 MWp
  • March - August 2018 – complete mechanic installation, DC + AC site

Melissant (NL)

  • 10 MWp
  • March - July 2018 – complete mechanic installation, DC + AC site

Vlieland (NL)

  • 1 MWp
  • May 2018 - complete mechanic installation (east/west system)

Lingemeer (NL)

  • 1,3 MWp
  • September - October 2017 – complete mechanic installation

Groeningen (NL)

  • 459 kWp
  • September 2017 – complete mechanic installation, ground screws delivery

Barton Place (UK)

  • 5 MWp
  • February – March 2017 – complete mechanic installation

Old Stone (UK)

  • 5 MWp
  • February – March 2017 – complete mechanic installation

Deerlijk (BE)

  • 141 kWp
  • November 2016 – complete mechanic installation

Siloth (UK)

  • 250 kWp
  • May 2016 – complete mechanic installation

North Lincolnshire (UK)

  • 0,47 MWp (Low Farm: 170 kWp, Frogmore: 100 kWp, Ingham Cliff Farm – 200 kWp)
  • December 2015 – complete mechanic installation, DC

GH Grain (UK)

  • 1,1 MWp
  • November 2015 – complete mechanic installation, DC

Renishaw – rooftop (UK)

  • 0,25 MWp
  • October - November 2015 – complete mechanic installation, DC

Ham Lane (UK)

  • 1,1 MWp
  • September 2015 – complete mechanic installation, DC

Ameland (NL)

  • 6 MWp
  • September - October 2015 – complete mechanic installation, DC

Tangmere (UK)

  • 5 MWp
  • August - September 2015 – complete mechanic installation

Raventhorpe (UK)

  • 10 MWp
  • February - March 2015 – pile driving (10 MWp), subconstruction and modules installation (5 MWp)

Roanhead (UK)

  • 3,5 MWp
  • February 2015 – subconstruction and modules installation

Hadlow (UK)

  • 18,9 MWp
  • December 2014 – March 2015 – complete mechanic installation

Aston House (UK)

  • 20 MWp
  • January – February 2015 – complete mechanic installation

Poulshot (UK)

  • 14,5 MWp
  • October - January 2015 – complete mechanic installation

Clearwell Farm - Newport (UK)

  • 0,6 MWp
  • August 2014 – complete mechanic installation

Barnstaple (UK)

  • 8,7 MWp
  • May 2014 - pile driving (ramming), partly sub-construction and modules assembly

Bodmin (UK)

  • 4,5 MWp
  • April 2014 - pile driving (ramming)

Shooters Bottom (UK)

  • 7,2 MWp
  • February 2014 - 27000 modules

Long Newnton (UK)

  • 7,2 MWp
  • February 2014 - pile driving (ramming) of a part, constructions, modules

Trewidland (UK)

  • 5 MWp
  • January 2014 - pile driving (ramming)

Trequite (UK)

  • 12 MWp
  • January 2014 - pile driving (ramming)

Brunsee (AT)

  • 1 MWp
  • October 2013 - pile driving (ramming)

Tewswoos (DE)

  • 1 MWp
  • September 2013 - pile driving (ramming)

Eppenstein (AT)

  • 1 MWp
  • September 2013 - pile driving (ramming)

Rottenmann (AT)

  • 1,5 MWp
  • August 2013 - pile driving (ramming)

Harman (RO)

  • 6 MWp
  • July/August 2013 - pile driving (ramming)

Magdeburg (DE)

  • 2 MWp
  • July/August 2013 - pile driving (ramming), sub-construction and modules assembly, DC

Neukirchen Vluyn (DE)

  • 3 MWp
  • July 2013 - pile driving (ramming)

Reghin (RO)

  • 1,5 MWp
  • June 2013 - pile driving (ramming)

Angern (AT)

  • 1,5 MWp
  • June 2013 - pile driving (ramming), sub-construction and modules assembly, DC

Turburea (RO)

  • 5 MWp
  • May 2013 - pile driving (ramming)

Ghindari (RO)

  • 2 MWp
  • March 2013 - pile driving (ramming)

Oberepfenbach (DE)

  • 1,2 MWp
  • November 2012 - pile driving (ramming), sub-construction, modules

Jichisu de Jos (RO)

  • 4,5 MWp
  • October-November 2012 - pile driving (ramming)

Chiriacu (RO)

  • 6,6 MWp
  • October-November 2012 - pile driving (ramming)

Ergolding (DE)

  • 3,3 MWp
  • October 2012 - pile driving (ramming), sub-construction, modules

Neuhardenberg (DE) - airport

  • 7,5 MWp of 145 MWp (largest PV project in Europe)
  • September 2012 - ramming (pile driving), sub-construction, modules

Vahldorf (DE)

  • 2,4 MWp on a depony
  • June 2012 – ground screws, sub-construction, modules

Schependorf (DE)

  • 12 MWp
  • May – June 2012 - pile driving (ramming)

Loitsche (DE)

  • 2,8 MWp on a hilly depony
  • May - June 2012 – ground screws, sub-construction, modules

Strasburg (DE)

  • 1,9 MWp
  • May – June 2012 – ground screws, sub-constructions, modules

Ahlhorn airport (DE)

  • 3300 piles
  • May 2012 – pile driving (ramming)

Haskovo (BG)

  • 4 MWp
  • April - June 2012 – pile driving (ramming)

Malevo (BG)

  • 2 MWp
  • April - June 2012 – pile driving (ramming)

Karlovo (BG)

  • 2 MWp
  • April - June 2012 – pile driving (ramming)

Panchevo (BG)

  • 2 MWp
  • April - June 2012 – pile driving (ramming), substructure and modules installation

Sliven (BG)

  • 2 MWp
  • April - June 2012 – pile driving (ramming), substructure and modules installation

Bad Driburg (DE)

  • 2 MWp
  • December 2011 – substructure and modules installation

Leutkirch (DE)

  • 5 MWp
  • November – December 2011 – ramming (pile driving)

Frankfurt am Main (DE)

  • 3 MWp
  • November – December 2011 – ramming (pile driving)

Kirchenwirt (DE)

  • 1,5 MWp
  • November – December 2011

Niepars, Rügen (DE)

  • 1,5 MWp
  • November – December 2011

Weeze (Goch) (DE)

  • 14 MWp
  • October – December 2011

Spreitenbach (Zürich) (CH)

  • 300 kWp
  • October – December 2011

Weddingstedt (DE)

  • 3 MWp
  • July-August 2011 – ground screws

Warnemünde (Rostock) (DE)

  • 2 MWp
  • July 2011

Holzgünz (Memmimgen) (DE)

  • 3 MWp
  • June 2011

Rožňava (SK)

  • 2 MWp
  • May 2011

Taviano (Puglia) (IT)

  • 1 MWp
  • May 2011

Jalsovik (SK)

  • 1 MWp
  • 2011

Viglas (SK)

  • 1 MWp
  • 2011

Ladovo (SK)

  • 5 MWp
  • 2011

Jalsovik II (SK)

  • 0,3 MWp
  • 2011

Trpin (SK)

  • 1,4 MWp
  • 2011

Vranovska Ves (CZ)

  • 16 MWp
  • 2010

Usilne (CZ)

  • 1 MWp
  • 2010

Mysliv (CZ)

  • 2 MWp
  • 2010

Ledenice (CZ)

  • 1,4 MWp
  • 2010

Straz pod Ralskem (CZ)

  • 3 of 8 MWp
  • 2010

Zalany (CZ)

  • 3,5 MWp
  • 2010

Dubi (CZ)

  • 5 MWp
  • 2010

Vidov (CZ)

  • 0,6 MWp
  • 2010

Vysokov (CZ)

  • 4 MWp
  • 2010

Jeníkov (CZ)

  • 5 MWp
  • 2010

Dynín (CZ)

  • 2,1 MWp
  • 2010

Pravčice (CZ)

  • 2,5 MWp
  • 2010

Zebrak (CZ)

  • 0,2 MWp
  • 2010

Vladislav (CZ)

  • 0,4 MWp
  • 2010

Hodonice (CZ)

  • 1 MWp
  • 2010

Tasov (CZ)

  • 2 MWp
  • 2010

Ralsko (CZ)

  • 4 of 55 MWp
  • 2010

Horgau (DE)

  • 5 MWp
  • 2010

Ernsthof (Tauberland Park) (DE)

  • 7 MWp
  • 2010

Kobyli (SK)

  • 1,5 MWp
  • 2011

Cenkov (CZ)

  • 1 MWp
  • 2010

Rybnice (CZ)

  • 0,3 MWp
  • 2010

Blatna (SK)

  • 1 MWp
  • 2010

Bojkovice (CZ)

  • 3 MWp
  • 2010

Rybniky (CZ)

  • 1,8 MWp
  • 2010

Tisice (CZ)

  • 0,2 MWp
  • 2010

Bruzovice (CZ)

  • 0,7 MWp
  • 2010

Prostejov (CZ)

  • 0,3 MWp
  • 2010